Wired electric roller shutters need a safe connection to the mains, and most installers use a qualified electrician for it. In England, a new circuit is notifiable building work under Part P, while adding a fused spur to an existing circuit outside special locations is not notifiable but must still meet the wiring regulations. Expect roughly £150 to £350 per connection. Solar shutters run from their own panel and battery, so they need no mains wiring at all.
Key points
- All electrical work must meet BS 7671, the wiring regulations.
- New circuits and consumer unit work are notifiable in England under Part P.
- A registered electrician can self certify and should give you a certificate.
- Solar shutters need no electrician.
Wired, plug in or solar
| Power | Electrician needed? | Typical extra cost |
|---|---|---|
| Hard wired to a fused spur | Yes, normally | £150 to £350 per spur |
| New dedicated circuit for several shutters | Yes, notifiable in England | £300 to £700 |
| Solar panel and battery | No | Included in the shutter price |
| Battery only (rechargeable) | No | Included |
What Part P says
Part P of the Building Regulations in England covers electrical safety in homes. Some work is notifiable, meaning building control must be told, either by a registered competent person electrician who self certifies the job or by applying to building control directly. Notifiable work includes installing a new circuit, replacing a consumer unit, and most new work in special locations such as bathrooms.
Connecting a shutter motor to an existing circuit through a fused connection unit outside a special location is usually not notifiable, but it still has to be designed, installed and tested to BS 7671. Wales has similar rules. Scotland and Northern Ireland have their own building standards, and a building warrant or approval may apply to some electrical work.
What a good installation looks like
- Cable routed neatly, ideally planned before plastering on new builds.
- A fused connection unit or isolator so each shutter or group can be switched off for maintenance.
- Cables through the wall sealed and protected where they enter the box.
- Switches located sensibly, or radio controls so no switch cable is needed.
- An Electrical Installation Certificate or Minor Electrical Installation Works Certificate handed over.
Choosing an electrician
Use an electrician registered with a government approved competent person scheme, such as NICEIC or NAPIT, so notifiable work can be self certified. Many shutter installers have an electrician on the team or one they work with regularly. Ask whether the electrics are included in the quote, and who provides the certificate.
If you want to avoid wiring altogether, choose solar. See solar roller shutters on UK brick.
Frequently asked questions
Do electric shutters need an electrician?
Hard wired shutters normally do. Solar and battery shutters do not need mains wiring.
Is fitting a shutter motor notifiable under Part P?
A new circuit is notifiable in England. A fused spur from an existing circuit outside special locations is usually not, but must still meet BS 7671.
How much does an electrician charge to connect shutters?
Typically £150 to £350 per connection, or more for a new circuit serving several shutters.
Can one switch control all my shutters?
Yes. Radio motors can be grouped on one remote, wall transmitter or app without extra wiring.